Find the workflow, evidence and engineering guidance for turning an existing PV site into a better decision.

/

Data centre co-location

Test IT capacity, power, fibre, cooling, footprint, heat and commercial structure.

Screen the infrastructure

  • Available import, export and firm-power concept.
  • Three to five fibre or interconnection candidates rather than nearest-only distance.
  • Facility footprint, access, cooling conditions and planning envelope.
  • PV supply, grid supply, BESS and backup topology.
  • IT load, utilisation, PUE and ownership or lease structure.

Read connectivity evidence honestly

Published PoPs, backbone routes, carrier-neutral facilities and estimated access routes are separate layers. Two nearby PoPs are not labelled diverse unless separate physical paths and entrances are carrier-confirmed.

Did this answer your question?

Your response helps PV8 improve the next guide.

Still need a hand?

Bring the decision, not a support ticket.

Tell PV8 what you are trying to decide and which asset or result is involved.
Contact PV8 →