Spain's 80% hourly rule: which solar plants can supply a data centre

What the decree approved on 20 November 2026 asks of large data centres, which plants count as their supply, and what a plant owner should check now.

Also available in Español

PV8 calculatorTry it on your plantEnter your plant's size and yearly production and see the data-centre load it could back in every hour. No account needed.

What was approved

On 20 November 2026 Spain's Council of Ministers approved a Real Decreto on the sustainability of data centres. It sets what a large data centre must show to obtain access and connection rights to the grid.

This guide follows the summary published that day by the Ministry for the Ecological Transition (MITECO). The official text had not been published when the guide was written, so thresholds and dates may differ once it appears in the Boletín Oficial del Estado.

What a data centre must show

  • The grid-access requirements apply to data centres with more than 10 MW of electrical power.
  • In every hour, 80% of the electricity consumed must be backed by renewable energy. The count is hour by hour, not a yearly average.
  • Self-consumption, storage and supply contracts of more than six years count towards the 80%.
  • The requirement lasts until renewables exceed 90% of Spain's electricity mix.
  • Certain breaches bring automatic compensatory charges on the centre's electricity bills, in proportion to the deviation. Sanctions can suspend its access and connection rights for up to three years.
  • Projects already in processing have six months to adapt, or three if they are waiting for a grid-access tender. The alternative is to give up their access and connection rights without their guarantees being called.

Which plants count as supply

The 80% must come from generation that joined the system no more than 36 months before the data centre starts operating. The ministry names three exceptions: photovoltaic plants, certain biomass plants and repowerings.

For an existing solar plant that is the line that matters: on the ministry's summary, its age does not rule it out.

  • A draft of the decree, as a law firm described it, attached a condition: the solar plant must hold no power purchase agreement (PPA) on the date the decree enters into force. The published text will show whether that condition remains.
  • The same draft counted repowerings that need a substantial revision of the connection agreement, with the 36 months running from that revision.
  • The first draft required producers to be in Spain, and the law firm's note records no change. We found no distance or zone requirement in any source.

Why storage changes the offer

A data centre draws about the same power day and night. A solar plant covers the daylight hours and none of the night, so solar alone cannot meet an every-hour requirement.

Storage counts towards the rule. A plant whose battery is charged from its own output can offer backed hours after sunset, which is what the buyer lacks. For scale: a 100 MW data centre needs 80 MW backed through a 14-hour December night, about 1,100 MWh.

A buyer will probably need more than solar: storage, and other renewable generation that meets the 36-month rule. A plant that covers more of those hours is closer to what such a buyer needs.

A lighter route for flexible data centres

For five years from the decree's approval, a data centre that joins the automatic power-reduction scheme (SRAP) and accepts priority disconnection may show a lower share: 60% in peak hours (P1) until 31 December 2028, then 70% in peak and shoulder hours (P1 and P2).

What a plant owner should check now

  1. Establish whether the plant holds a power purchase agreement (PPA) today, when it began and when it ends. Keep the documents. The draft's condition turns on the date the decree enters into force, which that draft set at twenty days after publication.
  2. If the plant receives specific remuneration, ask counsel how a supply contract would affect it. No source we read answers this.
  3. Check the buyer's size. On the ministry's summary, only data centres above 10 MW need this supply. The draft also counted grouped data centres of one owner.
  4. Expect a long contract: the ministry says more than six years, the draft a minimum of six. The draft also asked for a public deed naming the plant and the data centre, and for the plant owner to redeem the plant's guarantees of origin at least once a year with the regulator (CNMC), naming the data centre's supply point (CUPS).
  5. Before pricing a battery or a repowering, compare the plant's output with a flat load hour by hour. Annual energy does not show what an every-hour buyer needs.

Where PV8 fits

PV8 has a public page where a plant owner enters the plant's size and yearly production and sees the data-centre load it backs in every hour, alone and with a battery or wind beside it. In a PV8 workspace the same screen appears with a Spanish plant's data-centre results. PV8 Watch does not yet track this decree.

What is still uncertain

  • The official text is not published. The figures in "What a data centre must show" are the ministry's summary.
  • The surcharge schedule discussed in earlier drafts has not been confirmed for the approved text.
  • A general election is due on 29 November 2026, and the main opposition party, the Partido Popular, has said it would repeal the decree.
  • The data-centre association SpainDC and the Madrid region have said they will challenge the decree in court and ask for its suspension.

Sources

Did this answer your question?

Your response helps PV8 improve the next guide.

Still need a hand?

Bring the decision, not a support ticket.

Tell PV8 what you are trying to decide and which asset or result is involved.
Contact PV8 →