Can your solar plant supply a data centre under Spain's 80% rule?

Spain's data-centre decree, approved on 20 November 2026. The official text is not yet published.

Data centres above 10 MW must back 80% of each hour's consumption with renewable supply. See what your plant could back.

How is that possible at all?

Solar alone backs nothing at night, so a centre that must back 80% of every hour needs supply that runs when the sun does not: wind, a battery that moves solar output into the evening and night, or the flexible route, which sets a lower share for named toll periods. Set it up below; every hour of a modelled year is counted.

The calculation runs in your browser and sends no figures to PV8; a link that holds them does reach the server's logs. Server logs and usage events are covered by the Privacy Notice.

The data centre
Your solar plant

Installed peak power, between 0.01 and 2,000 MWp.

Use your metered figure if you have it.

Does the plant hold a power purchase agreement (PPA) today?
Added supply

New capacity counts for a centre that starts operating within 36 months of that capacity joining the system.

The flexible route

For 5 years, the centre backs a lower share in named toll periods (P1, and from 2029 P1 and P2) and accepts priority disconnection on the system operator's signal. No source says whether anything is required outside those periods.

Rule in force

74% of the year's hours backed at 80%: 6,533 of 8,760

Over the year, the supply matches 71.2% of the centre's consumption, all hours taken together.

To be backed in every hour, the centre could draw at most 3.7 MW from this supply, not 12 MW.

  • Wind adds 23.4 percentage points of hours backed.
  • The battery adds 26.6 percentage points of hours backed.
Month by month on the standard route
MonthHours backedShortfallSurcharge tier (draft)
January45925%70%
February40032.6%70%
March62811.5%30%
April6417.4%15%
May6756.9%15%
June60112.9%30%
July6727.2%15%
August6657.3%15%
September56915.9%30%
October53422%70%
November42429.2%70%
December26541%70%

Shortfall: each hour's distance to the 80% share, averaged over the month. Tier: the revised draft's surcharge rate for that monthly shortfall, plus 10 points for each further year in a row. No source read says what amount the surcharge is charged on.

Would a battery, wind or a repowering pay on your plant?

A PV8 workspace compares continued operation, repowering and storage using your generation history, equipment and grid terms, and tests wind around the PV you keep.

Start my workspace →

Opens PV8's registration. Your interest in data centres in Spain carries over; your plant figures do not.

Signing up shows a first result for one plant of any size, before a payment card is asked for. To keep a workspace, Basic covers one plant up to 10 MWp; for a larger plant, ask PV8 through the form below.

or ask PV8 to look at it with you

Ask PV8 to look at it with you

A person at PV8 reads every message and replies by e-mail. There is no automatic reply.

PV8 will receive your name, your e-mail and this text:


PV8 stores this message and uses it to reply to you. Privacy Notice

Developing a data centre and looking for supply that counts? Use the same form

What this result rests on

Rule status
Approved by the Council of Ministers; official text not yet published
Instrument
Real Decreto por el que se regulan los requisitos de sostenibilidad energética, medioambiental y de resiliencia y soberanía digital aplicables a los centros de datos

Limits of the evidence and open questions

The decree was approved on 20 November 2026 and its official text was not published when these rules were recorded: the values come from the ministry's summary and, where the open questions say so, from a law firm's note on the revised draft. Screening profiles are labelled synthetic shapes; contract structure, metering and the published text govern actual compliance. Not legal advice.

  • No article of the approved text has been read: it was not in the Boletín Oficial del Estado on 20 November 2026. Every value here comes from the government's summary or from a law firm's note on an earlier draft.
  • The photovoltaic exemption's condition comes from the revised draft, not the ministry's summary.
  • Whether a plant receiving specific remuneration may sell under such a contract, and what that does to its regulated income, was not found in any source.

The solar shape is modelled. The wind is the 2023 ERA5 reanalysis for one site in the Ebro valley (Aragón), through a published turbine power curve, set to the Spanish wind fleet's average output that year. It stands in for wind anywhere in Spain, so your site's wind will differ: in September and October this site ran at about half the fleet's level. Neither is your plant's metered data. The test covers every hour of the year. Wind data: ECMWF, Copernicus Climate Change Service, CC BY 4.0 (creativecommons.org/licenses/by/4.0). Contains modified Copernicus Climate Change Service information 2023; neither the European Commission nor ECMWF is responsible for any use made of it.

This is a screening result, not legal advice. The published text and your contracts decide what counts.

PV8 uses specialist engineering and commercial engines to uncover and test new value routes for operating PV assets and ready-to-build projects.

Read the guide: Spain's 80% hourly rule and which solar plants can supply a data centre →