PV8Greece · Data centres
Annual renewable supply assessment
Fictional worked example ·
Inputs and assumptions
- Prepared for
- Data centre developer
- Project phase
- Connection stage on 17 November 2026
- New or planned application
- Demand basis
- 10 MW average facility load × 8,760 hours
- Annual facility electricity demand
- 87,600 MWh
- Proposed annual renewable allocation
- 50,000 MWh
- Evidence status
- Full allocation reported as checked
Annual supply estimate
- 60% of annual facility demand
- 52,560 MWh
- Coverage from documented MWh
- 57.1%
| Annual MWh | If the proposed supply qualifies | On the evidence reported |
|---|---|---|
| Renewable supply | 50,000 MWh | 50,000 MWh |
| Gap to the target | 2,560 MWh | 2,560 MWh |
Next actions
- Check the offer date and the filing deadline for the physical-delivery agreement and technical report.
- Retain the dated plant, aid and allocation records that support the entered volume.
- Seek additional generation for the gap that remains even if the proposed supply qualifies.
Documents to prepare
- Plant ID and dated operating licence or energisation certificate, final connection offer and commissioning schedule.
- Evidence of operating aid, existing contracts and the annual MWh still available.
- Once a buyer is identified, compare the plant’s dates with the centre’s grid application, agreement and energisation.